RTA awards contracts for Phase 4 & 5 of Dubai Water Canal costing AED703m #Dubai - Dubai City Guide
Guest Posts, Link Building, SEO, Pay-Per-Click campaigns
Advanced Search
Home / News / Company News
Company News
   

RTA awards contracts for Phase 4 & 5 of Dubai Water Canal costing AED703m
(28 May 2016)

 

Roads and Transport Authority (RTA) has awarded a contract for Phase 4 and 5 of the Dubai Water Canal Project. This steps falls within the  implementation of the directives of HH Sheikh Mohammed bin Rashid Al Maktoum, Vice-President, Prime Minister of the UAE and Ruler of Dubai, to construct the Dubai Water Canal, upgrade the infrastructure of the area, and complete the project within the timeline set,. According to the contract, which amounts to AED703 million, works in both phases are set for completion by the end of September this year.

Highlighting the latest phases of the project, HE Mattar Al Tayer, Director-General and Chairman of the Board of Executive Directors of RTA said: “Phase 4 of the Dubai Water Canal project, which costs about AED307 million, is part of infrastructural works required to serve property development areas on both sides of the Canal, including roads & utility lines. The Canal stretches 3.2 km from the Business Bay Canal up to the Arabian Gulf via the Sheikh Zayed Road (SZR), Al Wasl Road and Jumeirah Road. Projects to be constructed on the Water Front will be served by modern water transport means, and result in improved quality of water in the Dubai Creek.

“Phase 5 of the Dubai Water Canal project, which costs about AED396 million would link the Business Bay Canal with the Dubai Water Canal terminating at the Arabian Gulf. Works include building quay walls of precast concrete slabs all along the stretch of the Canal, and completing & diverting utility lines & key services to give way for completing the construction works of the Canal as well as the removal of impacted services. Works also include the treatment of hyper-saline water of the Business Bay Lakes, removing sand barriers in the course of the Canal, and constructing three marine transport stations on both sides of the Canal,” explained Al Tayer.

Work Progress
Construction works in the Dubai Water Canal are progressing according to the approved time chart, and the completion rate has reached 92% in the Bridge of the SZR. RTA has recently opened the northern bridge of the SZR in the direction from Abu Dhabi to Dubai. Completion rate in the Abu Dhabi-bound southern bridge has reached 81%, and the bridge is expected to be opened in July this year. 

The contract of Phase 1 of the project comprises the construction of a bridge of 8 lanes in each direction on the Sheikh Zayed Road crossing over the Canal in a way allowing free navigation round-the-clock. It also includes modifying lanes of affected roads to ensure integrated traffic movement between the two shores of the Canal. An 800 meter-long sector of the SZR will be affected by this project phase, which also includes diverting the existing utility lines affected by the Canal course, fitting smart light controlled via a smart app, in addition to fountains on the bridge.

Works under Phase 2 of the project, include constructing bridges on Al Wasl and Jumeirah Roads are progressing according to the approved timetable with completion rate has so far clocked 86%. The contract of this Phase encompasses the construction of bridges on Al Wasl and Jumeirah Roads crossing over the Water Canal with vertical clearance allowing the passage of boats up to 8 meter-high. It also includes the construction of a free multi-tier interchange to link the traffic movement between Al Wasl, Al Hadiqa and Al Aathar Roads to ensure a smooth traffic flow instead of the existing light signals. The contract includes the construction of bridges linking with the proposed peninsula to the south of the Jumeirah Park, diverting utility lines via conduits passing underneath the Canal, in addition to laying spare utility ducts under the Canal to cater to projected future needs.

Completion rate in Phase 3 of the Dubai Water Canal Project has exceeded 75%, and works are well underway to complete the construction of quay walls, protect the utility lines, divert sewage lines on both sides of the Canal, build a sewage pumping plant, and construct a coastal breakwater. Works under Phase 3 also include drilling the Water Canal, building quay walls, and constructing 3 pedestrian bridges linking the two sides of the Canal at key locations to ease the mobility of people, and encourage them to use mass transport means, especially marine transit modes. Works also include constructing 10 marine transit stations to enhance the role of marine transit modes in the movement of people, especially after the completion of several of islands in the Arabian Gulf, such as The World and Jumeirah 2. The marine transit modes are expected to lift more than 6 million passengers annually in that area. Phase III also includes landfilling works to build a man-made peninsula along the Jumeirah Park, which will double the beach line of the Park, increase the park area, and make a room for more leisure activities.

We accept Guest Posts


DubaiCityGuide.com is owned and managed by Cyber Gear



  All fields are mandatory
Your Name
Email
City
Country
Your Comments
 Max 250 characters - Word Count :
Image Verification
Change Image

     
 
email print
 

Sponsored By : PressReleaseNetwork.com           Sponsored Opportunities

       
       
   
       

Hotels hotels Check out Hotels in Dubai
Shopping shopping A complete Mall & Store Guide
Dining dining Eating out at the coolest spots
Sightseeing sightseeing Things to see & do
DCG Recommends dcg recommends Best of the best in Entertainment
News Alerts
News Alerts
Stay ahead with dubai news
dcg mobile
dcg Mobile
With you wherever you go
rss feed
RSS Feeds
Get the latest
dubai blog
Dubai Blog
Your space, your voice
sitemap
Sitemap
DCG at a glance